VOlUME 03 ISSUE 09 September 2024
Andriansyah
Pamulang University
DOI : https://doi.org/10.58806/ijsshmr.2024.v3i9n13Google Scholar Download Pdf
ABSTRACT
This study aims to determine the productivity value of construction workers of PT Bima Natisa Graha red brick installation work on the construction project of housing units in residential area projects, to determine the factors that hinder the productivity of construction workers for red brick installation and to determine the productivity value of construction workers in red brick installation work after improving the factors that hinder the productivity of construction workers in red brick installation. The method to measure the productivity of construction workers in the installation of red bricks with the time study method. Time study is a method of measuring labor productivity in the field by determining the standard time of a job. The results of the study can be concluded as follows: (1) The productivity value of construction workers for red brick installation work on a housing construction project implemented by the contractor PT Bima Natisa Graha on a type 60 housing unit with a time study method of 0.378 M2 / OJ (2) Factors that hinder the productivity of construction workers are site managers, implementers and foremen from PT. Bima Natisa Graha who is rarely seen at the project site which should be in charge of giving directions in carrying out work in the field to workers so that workers joke more, talk a lot, smoke a lot, play a lot of cellphones and have coffee during working hours, this condition occurs because there is no reprimand and direction from the authorities. (3) The productivity value of construction workers for red brick installation work on a housing construction project carried out by the contractor PT Bima Natisa Graha on a type 60 housing unit with the time study method after productivity improvement is 0.496 M2 / OJ.
KEYWORDS:Productivity, Construction Labor, Time Study Method, Factors Affecting Construction Labor Productivity
REFERENCES
1) Saputra, T. A., & Anwar, S. (2020). Analisis Manajemen Konstruksi Pada Bendung Copong Kabupaten Garut. Jurnal Konstruksi dan Infrastruktur, 8(2).
2) Kiswati, S., & Chasanah, U. (2019). Analisis konsultan manajemen konstruksi terhadap penerapan manajemen waktu pada pembangunan rumah sakit di Jawa Tengah. Neo Teknika, 5(1).
3) Caroline, D., & Sulistio, H. (2018). Pengaruh Peningkatan Produktivitas Terhadap Durasi Fabrikasi Besi Pada Proyek Indonesia 1 Dengan Crew Balance Chart. JMTS: Jurnal Mitra Teknik Sipil, 1(1), 1-8.
4) Malamassam, L. (2016). Analisa Produktivitas Pekerja Dengan Metode Time Study Pada Proyek Pembangunan Gedung Teknik Industri ITS (Doctoral dissertation, Institut Teknologi Sepuluh Nopember).
5) Amalia, K. R., & Suryani, S. (2021). Analisis Perbandingan Produktivitas Tenaga Kerja Lokal Dengan Tenaga Kerja yang Didatangkan Dari Luar Kota Jambi. Jurnal Talenta Sipil, 4(1), 66-73.
6) Cahyadi, H., Purnamasari, E., & Nordiansyah, M. (2021). PERHITUNGAN PRODUKTIVITAS PEKERJAAN PEMASANGAN DINDING BATA RINGAN DENGAN METODE TIME STUDY PADA PROYEK PEMBANGUNAN RUANG KANTOR SEKOLAH MENENGAH ATAS NEGERI 5 BANJARMASIN.
7) Robbins, S. (2017). Management: l'essentiel des concepts et pratiques/Stephen P. Robbins,... Mary Coulter,... David DeCenzo,...[et al (p. 1). Pearson.
8) Sugiyono. (2017). Metode Penelitian Pendekatan Kuantitatif, kualitatif, dan R&D. Bandung: Alfabeta.
9) Matondang, D. R. U. (2017). Analisis Perbandingan Produktivitas Kerja Tukang Pada Proyek Konstruksi Di Medan Dan Pematang Siantar.
10) Anggraini, A. (2018). The Analysis of Premium Strategy and Vehicle Claims in Increasing Revenues of PT Asuransi Sinar Mas Tangerang. Scientific Journal Of Reflection: Economic, Accounting, Management and Business, 1(3), 251-260.
11) AFANDI, B. (2018). ANALISIS PRODUKTIVITAS KELOMPOK PEKERJA PADA PEKERJAAN PEMBESIAN DAN PEMASANGAN BEKISTING DENGAN METODE TIME STUDY (Studi kasus Proyek Pembangunan PLTU Sofifi 2x3MW, Maluku Utara) (Doctoral dissertation, Universitas Mercu Buana).
12) Ervianto, W. I. STUDI EFEKTIFITAS KELOMPOK TUKANG PADA PEKERJAAN KOLOM BULAT.
13) Pramudiyanto, A., Hasyim, M.H., & Suryo, E.A. (2018). Optimalisasi Biaya Dan Waktu Pada Pelaksanaan Pekerjaan Pasangan Dinding Bata Merah Dengan Metode Time Study.
14) Erliana, C. I. (2015). Bahan Ajar Analisa dan Pengukuran Kerja. JURUSAN TEKNIK INDUSTRI FAKULTAS TEKNIK UNIVERSITAS MALIKUSSALEH.
15) WIJAYA NABABAN, T. R. (2014). STUDI EFEKTIFITAS KELOMPOK TUKANG PADA PEKERJAAN BALOK PADA PROYEK VIVO APARTMENT (Doctoral dissertation, UAJY).